The China-Laos railway crosses Mekong River twice on north of Luang Prabang, with the Luang Prabang bridge and Ban Ladhan bridge under construction.
In the other relevant development, the last pier foundation of the Ban Ladhan railway bridge over Mekong River, some 240 km north of Vientiane, has completed concrete casting on July 4, and the pier has risen above flood level last Sunday.
To some degree, construction of bridges and tunnels is the decisive factor of whether the China-Laos railway can be built on schedule. The China-Laos railway has a total length of more than 414 km comprising 60 percent of bridges and tunnels, linking Mohan-Boten border gate in northern Laos and the capital of Vientiane.
The China-Laos railway is being promoted by the leaders of the two countries as a project of interconnectivity. Since the commencement of construction in December 2016, the building of tunnels, bridges, roadbeds and other sections has progressed smoothly along the route.
The operating speed of trains on the route is designed to be 160 km per hour. The railway is expected to be fully operational in December 2021.
【国际英语资讯:Chinese constructors complete foundation of cross-Mekong River super bridges】相关文章:
★ 山寨也能成大器
★ 披着狮皮的驴The ass in the lions skin
最新
2020-09-15
2020-09-15
2020-09-15
2020-09-15
2020-09-15
2020-09-15